By June 2021, the Santa Cruz County Sanitation District will repair or replace a minimum of 10,000 linear feet of sewer mains, rated poor or worse, to protect water quality and public health.

VERIFICATION LINK/DOCUMENTATION

Key Steps

1 2 3 4
Identify sewer pipers to be included in pipe rehabilitation projects. Prepare plans, specifications, estimates (PS&E), and develop project budgets. Seek environmental clearances, bid and construct the pipe rehabilitation projects.  
Plan Reference: Collaborating Depts:
Target:
Baseline: Progress:
4.B.i, 4.C.ii HSA 10,000 Linear Feet 1 118% (11,789)