Road Resurfacing

By June 2021, Public Works will resurface 25 miles of county-maintained roadways.

Verification link/documentation

Key Steps

1 2 3 4
Perform Baseline Survey of PCI (Pavement Condition Index) for all County Maintained Roadways. Create a five year countywide Pavement Management Plan. Complete Plans, Specifications and Estimate (PS&E) package and obtain board permission to advertise projects. Advertise projects, open bids and award contracts.
Plan Reference: Collaborating Depts:
Target:
Baseline: Progress:
3.C.i PLN 25 Miles 1 111% (27.55)